DSO Building Update: April 1-5, 2019

This week's activities: Handicap signs north parking lot Irrigation system south of building. Wood inserts at north columns. Landscaping throughout the building. Fire lane signs. Fire alarm system throughout the building. Next week's activities: Final inspections. Turnover building.

DSO Building Update: March 25-29, 2019

This week's activities: Asphalt south parking lot Irrigation west of building. Striping south parking lot. Landscaping throughout the building. Limestone signs. Fire lane striping. Next week's activities: Continue striping throughout parking lots. Continue landscaping. Continue final inspections. Continue concrete color patio.

DSO Building Update: March 11-15, 2019

This week's activities: Limestone west bldg. D. Irrigation north of building. Light poles at south parking lot. Landscaping west building D. Louver enclosures at dumpster gate. Formwork and rebar for pathways. Next week's activities: Continue sidewalks at north and south of building. Continue grading for sidewalks thru the building. Continue louver enclosures at condensing units. … Continue reading DSO Building Update: March 11-15, 2019