This week’s activities:
- Handicap signs north parking lot
- Irrigation system south of building.
- Wood inserts at north columns.
- Landscaping throughout the building.
- Fire lane signs.
- Fire alarm system throughout the building.
Next week’s activities:
- Final inspections.
- Turnover building.